Staging of the Burrendah Park Ancillary Works is broken down into phases.

Expected timeline

Stage Work Expected timeframe
Community Piazza Stage 1
  • New forecourt
  • Toilets for the netball and tennis club
  • Western and southern car park works
  • Bowls club fence
  • Community engagement on skate plaza 
December 2019 – February 2020
Community Piazza Stage 2
  • Skate plaza
  • Burrendah Boulevard upgrade
  • Northern car park upgrade and extension
  • New bowls club fence
2020 – 2021
Community Piazza Stage 3
  • Active laneway
2022