Expected timeline

Stage

Work

Expected timeframe

Status 

Community Piazza Stage 1
  • New forecourt
  • Toilets for the netball and tennis club
  • Western and southern car park works
  • Bowls club fence
  • Community engagement on skate plaza 
December 2019 – March 2020  Complete 
Tennis clubhouse 
  • Tennis clubhouse improvements 
December 2020 - February 2021   
North oval shelter
  • North oval shelter improvements 
December 2020 - February 2021   
Burrendah Boulevard upgrade
  • New roundabout into the Willetton Stadium’s southern car park
  • Wider footpaths, designated pedestrian crossing points, a cycle path and increased street lighting along Burrendah Boulevard
January 2021 - March 2021  
Community Piazza Stage 2
  • Skate plaza construction 
  • Southern car park upgrade 
January 2021 – June 2021   
Community Piazza Stage 3
  • Active laneway
2022  