Expected timeline

Stage

Work

Expected timeframe

Status 

 Community Piazza Stage 1
  • New forecourt
  • Toilets for the netball and tennis club
  • Western and southern car park works
  • Bowls club fence
  • Community engagement on skate plaza 
 December 2019 – March 2020    Completed March 2020
 Southern car park upgrade 
  • Building 20 new car parks 
 November 2020 - Octpber2021   Completed August 2021
 Tennis clubhouse 
  • Refurbishment works
  • Enclosure of veranda area to increase clubroom size
  • Build of new internal coaches room
 December 2020 - February 2021    Completed 24 March 2021
 North oval shelter improvements 
  • Extension and re-roof of existing shelter
  • Build of new kitchenette, universal access toilet and storage
  • Build of disability parking
  • Build of stair connection from shelter to oval level
 December 2020 - February 2021    Completed 9 April 2021 
 Willetton Skate Park bowl removal
  • Removal of existing skate bowl
 First week of January 2021 – February 2021  Completed 7 January 2021 
 Temporary skate facility install
  • Temporary skate facility designed and installed in the precinct.
 December 2020 - October 2021  Removed when skate plaza completed September 2021 
 Burrendah Boulevard works
  • Drainage works
  • Landscaping
  • Build of new roundabouts and improved access into the Willetton Stadium
  • Expansion of southern and northern car park
 First week of January 2021 – June   2021  Completed October 2021 
 Community Piazza Stage 2 construction 
  • Removal of the western car park, with construction lay down and also the pop up interim skate park in the lane between the Willetton Tennis and Bowling club (active laneway)
  • Six car bays will be kept open in the Northern end of the active laneway
  • Build of new, integrated skate and pedestrian plaza. The plaza will extend from the forecourt outside the Willetton Stadium and replace the existing western car park next to the Stadium
 January 2021 - June 2021 
 
  Completed 4 October 2021 
 Community Piazza art
  • Public art installation 
 February 2021 - May 2021   Completed 10 October 2021
 Community Piazza Stage 3
  • Active laneway
 FY2023  2023 to 2024 - Completion 2025