Expected timeline

Stage

Work

Expected timeframe

Status 

Community Piazza Stage 1
  • New forecourt
  • Toilets for the netball and tennis club
  • Western and southern car park works
  • Bowls club fence
  • Community engagement on skate plaza 
December 2019 – March 2020  Complete 
Southern car park upgrade 
  • Building 20 new car parks 
17 - 27 November 2020  Complete 
Tennis clubhouse 
  • Refurbishment works
  • Enclosure of veranda area to increase clubroom size
  • Build of new internal coaches room
December 2020 - February 2021  In progress
North oval shelter improvements 
  • Extension and re-roof of existing shelter
  • Build of new kitchenette, universal access toilet and storage
  • Build of disability parking
  • Build of stair connection from shelter to oval level
December 2020 - February 2021  In progress
Willetton Skate Park bowl removal
  • Removal of existing skate bowl
First week of January 2021 – February 2021 In progress
Temporary skate facility
  • Temporary skate facility designed and installed in the precinct.
December 2020 - February 2021 In progress
Burrendah Boulevard works
  • Drainage works
  • Landscaping
  • Build of new roundabouts and improved access into the Willetton Stadium
  • Expansion of southern and northern car park
First week of January 2021 – June 2021 In progress
Community Piazza Stage 2 construction 
  • Removal of the western car park, with construction lay down and also the pop up interim skate park in the lane between the Willetton Tennis and Bowling club (active laneway)
  • Six car bays will be kept open in the Northern end of the active laneway
  • Build of new, integrated skate and pedestrian plaza. The plaza will extend from the forecourt outside the Willetton Stadium and replace the existing western car park next to the Stadium
January 2021 - June 2021 
 
 
Community Piazza art
  • Public art installation 
February 2021 - May 2021   
Community Piazza Stage 3
  • Active laneway
2022  