Works to complete the Southern Link Road Stage 1 Street Lighting project are anticipated to start on 1 April 2019 and are anticipated to be finalised by the end of May. There will be minimal disruption to traffic.

These works will include the completion of Street Lighting for the Stage 1 roundabout as well as path paving re-instatement and will increase visibility for the intersection.

All current works are located outside of the DWER permit areas and are required to provide safer vehicle movements in and around the Westfield Shopping Centre, the Greyhounds and Bunning’s.

The finalisation of Stage 1 works will also accommodate preparatory drainage works for the adjacent Stage 2. This drainage connects with existing pipes and are required to be installed at a lower elevation than the electrical conduits.

Stage 2 road works are yet to be scheduled and are subject to a Department of Water, Environment and Regulation (DWER) Native Vegetation Clearing Permit.