Staging of the Willetton Sports Precinct works is broken down into financial years and quarters.

Year 1 (July 2018 to June 2019)

Quarter 2 – October – December 2018

Netball and tennis courts
  • Netball courts relocated to within tennis courts area
  • Four tennis courts will become dual-use tennis/netball courts
  • Majority of existing courts are resurfaced
  • New fencing is installed
  • Access to half of the tennis courts will be restricted from November 2018 to end of January 2019
  • Disruptions to traffic flow will be spasmodic and timed to minimise userinconvenience
  • Redevelopment will allow the Clubs to better develop and grow membership
Car park upgrades
Interconnecting car park
  • Two tennis courts will be replaced with an interconnecting car park
  • Interconnecting car park construction (to connect north and south of Park) is expected to commence in October 2018 and is anticipated to be complete in November 2018
  • Disruptions to traffic flow will be sporadic and timed to minimise userinconvenience.
Bowls Club carpark
  • Construction starts on Bowls Club carpark end November.
Other works
  • Start of WBA Stadium expansion. The project is expected to commence in November and is anticipated to be complete in March 2020.
  • Commencement of planning and design of new Bowls Carpark and synthetic green

Quarter 3 – January - March 2019

Netball and tennis courts
  • Majority of existing courts are resurfaced
  • New netball and tennis net posts
  • Construction finishes by end of January 2019
Other works
  • Continued work on WBA Stadium expansion. The project anticipated to be complete in March 2020.
  • Planning and design commences for the Southern Changerooms refurbishment
  • Planning and Design commences for the Tennis Clubhouse redevelopment
  • Continued work on the Bowls Carpark – construction is anticipated to commence in March 2019 and be completed by June 2019

Quarter 4 – April - June 2019

Car park upgrades
  • Continued construction of Bowls Club car park. The project is anticipated to be complete in June 2019.
  • Continued work on the planning and design of the Southern changerooms
Other works
  • Construction starts on bowls club synthetic green. The project is expected to commence in April 2019 and is anticipated to be complete in May 2019
  • Continued work on WBA Stadium expansion. The project is anticipated to be complete in March 2020.
  • Continued work on the planning and design for the Tennis Clubhouse redevelopment

Year 2 (July 2019 to June 2020)

Quarter 1 – July - September 2019

Other works
  • Start of tennis clubhouse redevelopment. The project is expected to commence in September 2019 and is anticipated to be complete by June 2020.
  • Continued work on WBA Stadium expansion. The project is anticipated to be complete in March 2020.
  • Start of Southern Changerooms redevelopment. The project is expected to commence in July 2019 and is anticipated to be complete by March 2020.
Western and Southern car parks (stage one)
  • Line marking for a turning and disabled bay to the Southern car park
  • Curbing, line marking and pathway to the Western car park
  • The project is expected to commence in October and is anticipated to be complete in November 2018

Quarter 2 – October - December 2019

Other works
  • Continued work on tennis clubhouse redevelopment. Project is anticipated to be complete by June 2020.
  • Continued work on WBA Stadium expansion. The project is anticipated to be complete in March 2020.
  • Continued work on the Southern Changerooms refurbishment and redevelopement. The project is anticipated to be complete in March 2020.

Quarter 3 – January - March 2020

Other works
  • Continued work on Southern Changerooms refurbishment. Project is anticipated to be complete in June 2020.
  • Continued work on WBA Stadium expansion. The project is anticipated to be complete in March 2020.
Car park upgrades
  • Southern car park (stage 2) refurbishment. Project is expected to commence in January 2020 and be complete in March 2020.

Quarter 4 – April-June 2020

Car park upgrades
  • Northern car park refurbishment. Project is expected to commence in June 2020 and is anticipated to be complete in June 2021.
Other works
  • Skate park redevelopment. This Project, after community / user consultation and subject to Council approval, is expected to commence in June 2020 and is anticipated to be complete in June 2021.
  • Burrendah Boulevard Street frontage upgrade. Project is expected to commence in June 2020 and is anticipated to be complete in June 2021.