Drainage
Ongoing maintenance to drainage systems is essential to prevent flooding of roads and properties.
The City of Canning is responsible for the management and maintenance of 600 kilometres of roads.
To make sure residents travel safely, the City allocates funds annually for the maintenance and upgrade of roads. This includes the construction of traffic management measures, which help provide comfortable travel within City limits.
Roadworks projects are underpinned by the City's Integrated Transport Strategy (PDF 8.7MB). This strategy considers all modes of transport and the movement needs of all users, now and in the future.
Project |
Estimated Start |
Estimated Finish |
| Lea Close – Fourth Avenue to Cul-De-Sac | 27/07/2026 | 28/07/2026 |
| Elbe Ct – Tudor Ave South to Cul-De-Sac | 27/07/2026 | 28/07/2026 |
| Fitch Rise – Pinetree Gully Road to Sac | 30/07/2026 | 31/07/2026 |
| Station St – Grey St to Intersection | 11/08/2026 | 12/08/2026 |
| Aries Ct – Aldam Crescent to Cul-De-Sac | 25/09/2026 | 29/09/2026 |
| Kewdale Rd – Orrong Rd to Welshpool Rd | 3/10/2026 | 5/10/2026 |
| Whyalla St – Augusta St to Gympie Wy | 8/10/2026 | 9/10/2026 |
| Augusta St – Roxby Ln to Acanthus Rd | 9/10/2026 | 10/10/2026 |
| Sheffield Rd East – Mcdowell St to Felspar St | 10/09/2026 | 11/09/2026 |
| South St – Roe Hwy to Bannister Rd | 31/10/2026 | 7/11/2026 |
| Metcalfe Rd – Nicholson Rd to Bridgeway Av | 17/11/2026 | 20/11/2026 |
| Rostrata Ave – Glenmoy Ave to Killara Dr | 7/12/2026 | 10/12/2026 |
| Nicholson Rd – Ranford Rd Intersection | 20/01/2027 | 22/01/2027 |
| Riverton Dr East – Riley Rd to Fern Rd | 27/01/2027 | 5/02/2027 |
| Barbican St East – Riverton Brdge to Tudor Ave | 12/02/2027 | 14/02/2027 |
| Marjorie Ave – Leach Hwy to Barbican St E | 15/02/2027 | 19/02/2027 |
| Marjorie Av – Barbican St E to Tribute St E | 15/02/2027 | 15/02/2027 |